摘 要
本文以库伦旗沙漠公路为依托,结合风积沙路基现场施工,对其施工工艺进行了概述,对风积沙最大干密度和含水量的实验列举了四种,并对其实验的方法进行了的描述。本文还列举了一些施工中的注意事项。另外针对风积沙路基施工过程中常遇到问题,进行了分析和解决。如风积沙路基施工中的洒水问题可以采用打梅花井,人工修筑挡水埝的方法,即保证了洒水均匀,又可以防止漏洒;运输中的环境污染问题可以对车辆顶部的风积沙表面洒水或覆盖帆布进行解决。
关键词:风积沙,沙漠公路,路基,施工,施工工艺
ABSTRACT
Based on Carr to rely on the desert highway, with aeolian sand roadbed construction site, its construction process was outlined. Aeolian sand of the largest dry density and water content of the four cited, and its experimental method of description. This paper also cited a 毕业论文http://www.751com.cn/ 论文网http://www.751com.cn/ , the analysis and solution. Such as wind piled sand roadbed construction of sprinklers can be used to fight Sika wells, construction of retaining Shanian artificial methods guarantee that the sprinkler uniform, can also prevent leakage onto; transport of pollution problems can be top of the right vehicles aeolian sand surface sprinkler coverage canvas or resolve.
Keywords : aeolian sand, the desert highway, embankment, construction, technology of construction
目录
前言 1
第一章 工程概况 2
第二章 风积沙的基本性质 3
2.1 风积沙的物理化学性质 3
2.2风积沙的力学性质 3
2.3风积沙的透水性 3
2.4风积沙的非塑性 3
第三章 风积沙的分类 4
第四章 路基填筑施工工艺 5
4.1施工流程 5
4.2施工工艺 5
4.2.1 施工准备 5
4.2.2 施工放样 7
4.2.3 测量放线 7
4.2.4 填前处理 7
4.2.5 填方路堤的施工 7
4.2.6 挖方路堑的施工 8
4.2.7 布土 8
4.2.8 整平和浇水湿润 8
4.2.9 灌水坠实 9
4.2.10 碾压 9
4.2.11 检测 10
4.2.12 封闭 10
4.2.13刷坡 10
第五章 风积沙路基的防护 11
第辣章 风积沙路基施工注意事项 12
第七章 存在的主要问题及解决方法 13
结论 15
致谢 16
参考文献 1299