摘 要:本设计主要讨论随着城镇化进程的日益加快,高层建筑发展迅速。本文就高层建筑施工技术从技术施工、节能施工和混凝土浇筑施工等方面进行了探讨和分析,具有较强的实用性和价值性,供参考结合实际施工管理中遇到的问题,提出对现场管理、施工管理的创新以及后期施工管理等几方面的认识及现场施工管理;施工管理是建筑产品,因此,上做好管理工作非常重要,包括技术管理人员做到令出必行,并介绍了建筑工程后期施工管理工作的特点、经验和具体措施。 60201
毕业论文关 键 词:建筑工程,施工管理,施工技术
Abstract: the main design combined with practical construction problems encountered in the management, proposes to the site management, construction management innovation as well as the later period construction management and other aspects of the understanding and the site construction management; construction management of building products, therefore, do a good job of management work is very important, including the technical management personnel to make a will, and introduces the construction engineering construction management in later stage work characteristics, experience and specific measures.
Keywords: construction engineering, construction management, construction technology
1 设计选题说明 4
1.1 选题原因说明 4
1.2 设计项目概况 4
1.3 设计目的和要求 4
1.4 设计重点和难点 4
2 设计依据 4
2.1 规范和标准 5
2.2 参考文献的选用 6
3 设计的技术路线 6
3.1 主要方法 6
3.2 施工部署 6
3.3 施工准备 6
3.4 主要分部分项施工技术方案 6
4 设计的价值 8
4.1 对专业学习的作用 8
4.2 对社会工作的作用 8
结论 9
致谢 10
参考文献 11
附录1:总平面布置图 12
附录2:施工进度表 13
1 设计选题说明
1.1 选题原因说明
太仓张江信息产业园项目在处理各个问题上都很及时得当,结合在学校学过相关知识和现场实习经验,为了更好的了解相关知识,经指导老师的点拨和建议,决定写该课题。
1.2 设计项目概况
太仓张江信息产业园研发楼总建筑面积69240㎡,占地面积23225.34㎡,首层建筑面积3835.84㎡。主楼13层,裙楼4-9层。本项目采用钢筋砼板式基础、桩基承台基础,抗震等级为1级,工程设防烈度为7度。建筑高度为55.65m。外墙面采用干挂石材、铝板、局部外墙涂料二次装修设计。屋面采用FSG防水保温板和聚苯乙烯泡沫塑料板复合保温层。工程目标:
1、质量目标:分部分项工程合格率100%,达到合格市优质工程标准。
2、安全目标:杜绝一切重大伤亡事故。
3、工期目标:科学组织施工,合理安排工序穿插,确保合同工期实现。 太仓市张江信息产业园项目研发楼施工组织设计:http://www.751com.cn/guanli/lunwen_65595.html