corresponding pipe duct valves.
Cooling load calculations should be based on the parameters in the application of project profiles Hongye software to draw cooling load ; determine the pision of air conditioning systems and system solutions should be determined by the actual advantages and disadvantages of the various parameters of the commercial plaza air conditioning system ; select the cold source , is based on data obtained Hongye software to choose ; design and calculation of wind systems , planning and design of the drawings , and through hydraulic calculations to verify ; indoor air supply and air distribution in the form of selected using air fan coil system , a new way of fan coil air supply with a single set of new air system, separate supply room ; design of water systems , plumbing layout should take into account the layout of each room , and the water system and planning ; duct system insulation and plumbing system design should comply with pipe insulation and corrosion requirements .
Detailed requirements are as follows : load calculation part: Hongye envelope HVAC load calculation software is not included in the new wind load , in order to avoid the calculation results with the actual value of the software to produce errors , and therefore need to be some correction to make office buildings cooling load range falls (80 ~ 120W / m²), winter heat load (40 ~ 100W / m²). New wind load should be calculated separately.
Air system components: the number of square units through each room and 30m ³ / (h • person ) fresh air to determine the fresh air of each room , and through the [ 2 ] determine the segment of new air damper tube size. Determination of the exhaust pipe is also true. Also need to be installed in accordance with the relevant specifications corresponding damper .
Water system components: the translation of each room by cooling water outlet pipe flow , estimate the corresponding pipe diameter, and identify the most unfavorable water cycle refrigeration cycle resistance calculations to determine the pump head .
Partially furnished room : the combination of design experience for a reasonable arrangement , aimed to facilitate daily operations and machine
maintenance.
Insulation , corrosion parts: determined in accordance with design specifications , its role is to avoid unnecessary loss of cold heat.
目录
0 绪论 1
0.1 空调设计背景 1
0.2 空调系统的发展方向 1
0.3本次设计的方向 2
1 系统方案的选择确定 3
2 工程概况 7
2.1建筑概况 7
2.2室内设计参数 7
2.3室外设计参数 7
3 空调负荷计算 9
3.1围护结构瞬变冷负荷计算原理 9
3.1.1外墙和屋面瞬变传热引起的冷负荷 9
3.1.2室内建筑冷负荷 9
3.1.3外窗瞬变传热引起的冷负荷 10
3.1.4设备散热形成的冷负荷 10
3.1.5新风冷负荷 11
3.2商场围护结构冷负荷计算 12
3.3各房间送风方式的确定 12
3.4 商业楼新风量和新风负荷的确定 13
3.4.1新风负荷计算举例 13
4 风机盘管加新风系统选型计算 15
4.1风机盘管系统选型计算 15
4.2新风机组的选型 18
5 空调风系统 19
5.1空调房间气流组织 19
5.2风口的布置 19
5.2.1新风入口注意事项 19
5.2.2风道的布置和制作要求 19 商业广场下层空调通风系统设计+CAD图纸(2):http://www.751com.cn/gongcheng/lunwen_12310.html