    摘要:本文介绍了贵阳轻轨2号线贵富区间右线隧道结构设计。本设计领域为贵阳市轨道交通2号线二期工程贵钢站~富源北路站区间暗挖隧道,右隧设计起讫里程:YCK37+949.301~YCK38+870.350,长921.049m,全隧采用暗挖法施工。该区间内隧道全长921.049m,隧道为双洞单线结构,线间距为10~15m,隧道拱顶埋深13~90m;于隧道YCK38+100附近设置施工竖井、隧道中部联络通道。本设计按照暗挖法的要求施工。本设计主要内容包括:隧道的平纵断面线型设计、隧道净空断面设计,隧道衬砌结构设计以及施工组织等。在进行了二次衬砌的结构计算时,可借助结构力学求解器。69812

    本设计获得以下结论:

    1.采用复合式衬砌,初期支护喷射26cm厚C25混凝土,二次衬砌采用40cm厚C35钢筋混凝土,初期支护与二次衬砌之间设附加防水层。

    2.使用结构力学求解器求解时,得到最大弯矩组合设计值:M_d=140KN∙m,及相对应的轴向力组合设计值:N_d=95.92KN

    3.配筋时,选每侧钢筋为22,布置两排钢筋。计算结果判定为大偏心受压构件,而其最大裂缝宽度为0.19mm。

    4.全随采用暗挖法进行开挖,并进行科学施工管理。经过验算,该隧道方案设计合理,衬砌结构配筋验算均满足要求。

    关键词: 暗挖法;复合衬砌;隧道设计;台阶法

    Language Learning

    Abstract: This paper introduces the design of the right-wing tunnel in Guiyang Light Rail Line 2. The design range is Guiyang City Rail Transit Line 2 Phase II Project Guichang Station ~ Fuyuan North Road Station area tunneling, the right tunnel design starting mileage: YCK37 +949.301 ~ YCK38 +870.350, long 921.049m, the tunnel using dark digging Construction of law. The length of the tunnel is 921.049m, the tunnel is a double-hole single-line structure, the line spacing is 10 ~ 15m, the tunnel arch depth is 13 ~ 90m; in the tunnel YCK38 + 100 near the construction shaft, tunnel middle channel. The design in accordance with the requirements of the construction method. The main contents of this design include: tunnel vertical profile design, tunnel clearance design, tunnel lining structure design and construction organization. And the structural mechanics solver software was used to calculate the structure of the secondary lining.

    The design gets the following conclusions:

    1. The use of composite lining, the initial support jet 26cm thick C25 concrete, secondary lining with 40cm thick C35 reinforced concrete, the initial support and secondary lining between the additional waterproof layer.

    2. Using the structural mechanics solver to obtain the maximum bending moment design value: M_d = 140KN ∙ m, and the corresponding axial force combination design: N_d = 95.92KN

    3. Reinforcement, the election of each side of the bar is 22, arranged two rows of steel. The calculation result was judged to be a large eccentric compression member, and the maximum crack width was 0.19 mm.

    4. Using excavation method for excavation, scientific construction management. After checking, the tunnel program design is reasonable, lining structural reinforcement check to meet the requirements.

    Key words: concealed method; composite lining; tunnel design; step method

    目录

    第一章 绪论 1

    1.1 课题的目的和意义 1

    1.2 国内外研究现状与水平 1

    1.2.1 国内隧道研究现状与水平 1

    1.2.2 国外隧道研究现状与水平 1

    1.3 发展趋势 2

    第二章 工程概述与地质概况

  1. 上一篇:贵阳轻轨2号线机小区间左线暗挖隧道结构设计+CAD图纸
  2. 下一篇:abaqus受压可屈服型钢棒的支撑性能研究
  1. 贵阳轻轨2号线机小区间左...

  2. 贵阳轻轨2号线富森区间单...

  3. 涟水县剑桥印象小区12号楼...

  4. 淮安市华祥新绿洲2号楼工...

  5. 贵阳国际城E2应用BIM技术施工过程模拟

  6. 贵阳国际城E2应用BIM技术的造价管理

  7. 某小区框架混凝土10层小高...

  8. 感应加热电源研究现状及发展趋势

  9. 桥梁工程英文文献和中文翻译

  10. 竞聘上岗在企业改革中的探索与实践

  11. 论反不正当竞争法对知识产权的保护和限制

  12. 我国金融危机的可能性和危机管理

  13. 仿人头像机器人文献综述和参考文献

  14. 新闻微信公众号的发展策略研究

  15. 时代国际大厦基坑围护方案设计

  16. 流动儿童学习适应问题研究+文献综述

  17. 城市高层住宅小区物业管...

  

About

751论文网手机版...

主页:http://www.751com.cn

关闭返回