摘要上海电大行政楼位于上海市上海浦东新区,为6层现浇钢筋混凝土框架结构,行政楼总建筑面积为4902m²,建筑高度26.55m(从室外地坪到屋面檐口)。其结构形式为现浇钢筋混凝土框架结构,安全等级为二级,设计使用年限为50 年;建筑物等耐火等级为二级。该行政楼主体结构采用钢筋混凝土现浇框架结构,柱网尺寸主要为4.8m×8.7m、3.6m×8.7m、3.3m×8.7m,总长度为41m,总宽度为20 m,占地面积为817平方米左右。梁、柱构件通过节点连接形成骨架结构,由梁、柱承受竖向和水平荷载,中间隔墙仅起文护作用。底层层高为4.8m,各标准层的层高为4.2m,楼梯的踏步数均取12,第一层的楼梯的踏步高为200mm,其余层的楼梯的踏步高为175mm,踏步均宽为250mm。楼梯的梯段均宽为1.80m,可以同时三人行走,中间休息平台宽为2.6m,扶手的高度为1m,宽度为1m。内部功能主要满足教师办公,建筑外形简洁朴实。一层主要为各类办公室,其余层则设有大型会议室。该楼主体结构采用钢筋混凝土现浇框架结构。基础采用柱下独立承台桩基础。在立面设计中,主要强调建筑的简洁、朴实和亲和的特点,建筑形体采用正方形造型,不追求复杂的装饰。考虑到行政楼楼对消防、管理、使用,交通设施等诸多多方面的综合要求,在设计本建筑的交通组织方面特作了适当的考虑。该建筑选择了良好的朝向和自然通风,保持室内有良好的空气质量。36110
毕业论文关键词:行政楼;框架; 建筑设计; 结构设计。
Abstract Shanghai university of electric power administration building is located in Shanghai pudong new area, Shanghai, is 6 layers of cast-in-situ reinforced concrete frame structure, the administration building with a total construction area of 4902 m squared, building height 26.55 m (from the floor to the roof eaves outside). Its structure form for the cast-in-situ reinforced concrete frame structure, the security level for the secondary, design use fixed number of year for 50 years; Buildings such as fire resistance rating for level 2. The administration building main body structure adopts the cast-in-place reinforced concrete frame structure, the main column grid size 4.8 m * 8.7 m, 3.6 m * 8.7 m, 3.3 m * 8.7 m, the total length of 41 m, the total width of 20 m, covers an area of 817 square metre. Beam and column through the nodes connected to the skeleton structure, the beam and column under vertical and horizontal load, the middle partition only a maintenance role. Underlying the height of 4.8 m, the standard layer of the height of 4.2 m, the stair step number 12, bottom of the first layer of the stair footfall is 200 mm high, the rest of the layers of the stair footfall is 175 mm high, step width is 250 mm. The stairs of the bench are 1.80 m wide, can three people walking, at the same time breaks platform width of 2.6 m, the height of the armrest is 1 m, width of 1 m. Internal function mainly meet the teacher office, the building shape concise and simple. A layer mainly for all kinds of office, the rest of the layer is equipped with large meeting room. The building USES the cast-in-situ reinforced concrete frame structure of body structure. The foundation USES the pile foundation under column independent pile caps. In the facade design, focuses on the characteristics of the construction is simple and unadorned and affinity, architectural image using a square shape, do not pursue the adornment of the complex. Considering the executive tower building of fire control, management, use, transportation facilities, and many other aspects of comprehensive requirements, in the design of the construction of traffic organization for due consideration. Chose good toward the building and natural ventilation, maintain good indoor air quality.
Key words: administration building; Framework; Architectural design; The structure design. 六层现浇大学行政楼建筑与结构设计计算书+CAD图纸:http://www.751com.cn/gongcheng/lunwen_34441.html