    3.2 Statistics on Scheduling Problems and Performance Measures

    3.2.1 Scheduling Problems

    Table 3 shows the distribution of scheduling problems that are involved under this category. As for the general FMS schedul- ing studies, the parts dispatching was a popular item, which attracted the attention  of many  authors.

    3.2.2 Performance Measures

    Both flow-time and tardiness related measures were employed most frequently as  the  performance  measures.  This  is shown in  Table 4.

    Table 3. Scheduling problem in multi-criteria scheduling    approaches.

    Scheduling Number of Reference Period

    problem publications number of

    publications

    Chryssolouris et al. [59] tested a modular system that  treated a production scheduling problem as a multi-criteria decision- making issue using a simulation model. The developed method attempted  to  model  the  decision-making  process,  at the work

      centre  level,  as  a  multi-criteria  decision  problem.  The simul-

    Parts  dispatching  8 [59],  [83],  [85– 1985–1999

    89], [91]

    Machine  selection 1 [84] 1990

    AGV  scheduling   3 [84],  [88],  [90]  1990–1996

    Table 4. Performance measures used in multi-criteria    approaches.

    ation model consisted of two different work centre configur- ations (i.e. one work centre, and five work centres) and com- pared the rule-based method with four dispatching rules, which were LCFS, FCFS, SPT, and LPT. The employed performance measures were average flow-time, WIP, number of jobs com- pleted, and mean tardiness. The results showed that  for one work centre, the SPT rule performed well, and in the case of

      five work centres, the rule outperformed all other dispatching

    Performance Number of Reference Period measures publications number of

    publications

    Flow-time  related 5 [59],  [84],  [86], 1988–1996

    [88], [90]

    Tardiness or tardy  5 [59],  [84],  [86], 1988–1999

    job related [87], [91]

    Utilisation  related 3 [83],  [84],  [87]  1985–1994 (including system,

    machine, station, etc.)

    Cost related 2 [87], [91] 1994  and 1999

    Inventory  related  1 [59] 1988

    Others 4 [59],  [83],  [87], 1985–1996

    [90]

    3.3 Review of  Related Publications

    Shanker and Tzen [83] found that random FMSs require bal- anced workloads to operate effectively. They studied a schedul- ing problem in an FMS that was considered to be a composite of two independent tasks: loading and sequencing. Formulations were  presented for  the  loading problem  with  two objectives:

  1. 上一篇:水辅助注塑系统英文文献和中文翻译
  2. 下一篇:连杆机构英文文献和中文翻译
  1. 超声雾化加湿系统英文文献和中文翻译

  2. 胎压监测系统英文文献和中文翻译

  3. 在线机器测量系统英文文献和中文翻译

  4. 水辅助注塑系统英文文献和中文翻译

  5. 流量测量系统英文文献和中文翻译

  6. 开口端纺纱系统中的锥形...

  7. 金属板料冲压模具计算机...

  8. 网络信息时代下的社会道德滑坡现象探究

  9. 知识产权保护对我国国际贸易的影响及对策

  10. 装配式混凝土建筑的发展研究现状

  11. 基于宏/微驱动模式的双电...

  12. 《青春照相馆》作品导演阐述

  13. AdaBoost算法基于DSP的嵌入式人脸检测

  14. SolidWorks+LS-DYNA缓冲材料冲击特性建模与分析

  15. 高考作文命题样式研究

  16. 论《西游记》中的孙悟空形象

  17. 液压支架试验台测控系统设计任务书

  

About

751论文网手机版...

主页:http://www.751com.cn

关闭返回